Legal update · Buying
Maharashtra tightens flat registration: OC, sanctioned plans and what buyers should check
On 12 October 2026, Maharashtra's Revenue Department directed every sub-registrar in the state to refuse registration of certain flat documents if the required approvals are missing, or if the flat's area in the deed is larger than the area on the sanctioned plan. Here is what that change means, and what to check before you pay.
What changed
The instruction is in a Revenue Department circular dated 12 October 2026. It followed a 22 September 2026 meeting chaired by Revenue Minister Chandrashekhar Bawankule, held to curb unauthorised construction and the sale of flats with a larger area than the approved plans allow. The government has said the aim is to protect buyers from financial loss.
The Times of India's Mumbai report of 13 October 2026 put the change in plain terms: flats in buildings without an occupation certificate would henceforth not be registered, and neither would flats whose area is larger than the sanctioned area. A more detailed Times of India report from Pune, published the next day, sets out the papers sub-registrars have been told to see, and it is worth reading that list carefully, because it is not a single "no OC, no registration" rule for every kind of flat.
The reports say the checks apply across Maharashtra, not only in Mumbai. They cover agreements for first sale, sale deeds, deeds of apartment, and transfer documents for units in construction projects. Joint Inspector General of Registration Rajendra Muthe told The Times of India that, earlier, sub-registrars could not refuse to register a document; with this circular, they can check the papers and refuse registration.
One rule is stated consistently across the reports: if the area of the flat written in the document is larger than the area in the sanctioned plan, the sub-registrar must refuse registration, even if the other required papers have been submitted. The circular also warns that a departmental inquiry will be started against a sub-registrar who knowingly registers documents of unauthorised construction without following the instructions.
Who it applies to, and which papers are required
The circular, reported as Circular No. 2026/Pr.Kr. 367/Mudrank-2, tells sub-registrars to refuse registration if the document is not accompanied by a set of supporting papers. Those papers differ depending on whether the project must be registered with MahaRERA under Section 3 of the Real Estate (Regulation and Development) Act, 2016.
If the project must be registered with MahaRERA. The Times of India's Pune report, and accounts that cite the circular's wording, say the documents must include the MahaRERA registration certificate or an occupancy certificate, along with the sanctioned building plan showing the area of the unit. A PTI report carried by ET Realty and CNBC-TV18 listed the registration certificate, occupancy certificate and sanctioned building plan together. We have not independently opened the official PDF on a government website, so we note that difference rather than treat one version as settled.
If MahaRERA registration is not required. The reports say the documents must include a construction permission or commencement certificate from the competent authority, the sanctioned plan showing the unit's area, a zone certificate, and a measurement or survey plan.
A PTI report also said that flats in unauthorised buildings that violate the Unified Development Control and Promotion Regulations (UDCPR), a development plan or a regional plan cannot be sold directly until the building is regularised. Buildings that cannot be regularised will not be treated as legal, and demolition proceedings may be started.
What it means if you are buying an under-construction flat
An occupation certificate is usually issued only when a building is ready to occupy. If every first-sale agreement needed an OC, sales in ongoing MahaRERA projects would stall at the sub-registrar. The more detailed reports of the circular do not read that way. For a project that must be registered with MahaRERA, they describe the MahaRERA registration certificate or an occupancy certificate, plus the sanctioned plan, as the papers the sub-registrar is told to look for.
So, according to those reports, a first-sale agreement in a registered MahaRERA project may still be presented for registration with the MahaRERA certificate and the sanctioned plan. Two checks still matter a great deal. The project must actually be registered with MahaRERA — the government has cited complaints about developers who sold without that registration. And the area in your agreement must not be larger than the area on the sanctioned plan, or registration should be refused.
Registration of an agreement is not the same thing as an occupation certificate. Ask when the OC is expected, and keep a copy of the MahaRERA certificate and the sanctioned plan with your papers.
What it means if you are buying a ready flat
If the building is complete, ask for the occupation certificate — or the occupancy or completion document the local authority actually issued — and the sanctioned plan before you go to the sub-registrar. For a MahaRERA-registered project, also take the registration certificate. Compare the flat area in the sale deed with the area on the plan. A mismatch can now stop the registration itself.
What it means for developers
Developers need the required set of papers ready at registration. First sales can be held up if the MahaRERA certificate or occupancy certificate, and the sanctioned plan, are not produced — or, where MahaRERA does not apply, if the commencement or construction permission, plan, zone certificate and measurement map are missing. Selling or documenting a larger area than the sanctioned plan can now block the deed. If a building is unauthorised or needs regularisation, PTI reports that a direct sale should not go ahead until that is resolved, and that buildings which cannot be regularised may face demolition proceedings.
What it means for resale
Transfer documents for units in construction projects are within the reported scope of the circular. If you are selling or buying a resale flat, go to the sub-registrar with the approval papers and a plan that matches the area in the deed. A missing paper or an area mismatch can delay or stop registration.
Older buildings without an occupation certificate are a known issue in Mumbai. The detailed reports list an occupancy certificate as one of the acceptable papers for MahaRERA projects, and list construction permission or a commencement certificate — not specifically an OC — for projects that do not need MahaRERA registration. Do not assume every older resale will be treated in the same way. Take the papers you have to a sub-registrar or an advocate and check before you pay a large token.
A practical checklist for buyers
- Ask for the occupation certificate. Get a copy of the OC, or of the occupancy or completion document the local authority issued. Keep it with your file, and do not rely on a verbal assurance that "the OC is on the way" if you are buying a flat that is already being sold as ready.
- Ask for the sanctioned plan and compare the area. Check that the area written in the agreement or sale deed is not larger than the area shown for that flat on the approved plan. If it is, the reports say the sub-registrar must refuse registration.
- Check the project on MahaRERA. If the project is required to be registered, look it up on the MahaRERA website and ask for the registration certificate. Confirm that the registration covers the building or phase you are buying in.
- If the project is not under MahaRERA, ask for the other approvals. That means the construction permission or commencement certificate, the sanctioned plan, a zone certificate, and a measurement or survey plan, according to the reports.
- Ask the planning authority how to verify the OC. In much of Mumbai that is the Brihanmumbai Municipal Corporation; in other areas it may be MHADA, CIDCO or another local authority. The BMC civic portal is at portal.mcgm.gov.in. Search paths on municipal sites change, so if you cannot find the record online, ask the seller for a stamped copy and how it can be verified.
- Do not treat the registration appointment as a formality. If papers are missing or the area does not match, the sub-registrar can now refuse to register. Get the file in order before you pay a heavy token or book a date. Our guide on the 10 documents to check before buying a flat in Mumbai is a useful starting list.
- If there is any talk of regularisation or unauthorised work, pause. Get advice from your advocate before you pay or sign.
Want the papers on a flat checked before you register?
Call or WhatsApp Chirag on 9920194725. Casa Ideal Real Estate, agent MahaRERA A51800000642.
Chirag Chhabria · Casa Ideal Real Estate · Agent MahaRERA A51800000642
This is general information, not legal advice. News reports of the circular differ on one or two points, and we have not independently opened the official government PDF. A techno-legal consultant, Sathyen Prasad, told The Times of India that a circular is an executive instruction and cannot supersede the statutory Act and rules that govern registration. The law and the facts of each case matter, so speak to your own advocate before you pay, sign or go to the sub-registrar.
Sources
- The Times of India, 13 October 2026: Maharashtra bans flat registration without occupation certificate
- The Times of India, 14 October 2026: Maharashtra bars document registrations for illegal buildings
- The Economic Times (ET Realty / PTI), 14 October 2026: Maharashtra government bars registration of documents related to unauthorised constructions
- CNBC-TV18 (PTI), 13 October 2026: Maharashtra government bars registration of documents related to unauthorised constructions
- StudyCafe, 14 October 2026: Maharashtra Government Bars Registration of Flats Built Without Permission or Beyond Sanctioned Plans (cites Circular No. 2026/Pr.Kr. 367/Mudrank-2)